Go to Database Directory || Go to CISG Table of Contents || Go to Case Search Form || Go to Bibliography

CISG CASE PRESENTATION

Germany 29 December 1998 Hamburg Arbitration proceeding (Cheese case) [translation available]
[Cite as: http://cisgw3.law.pace.edu/cases/981229g1.html]

Primary source(s) of information for case presentation: Case text

Case Table of Contents


Case identification

DATE OF DECISIONS: 19981229 (29 December 1998)

JURISDICTION: Germany

TRIBUNAL: Schiedsgericht Hamburger Freundschaftliche Arbitrage [Arbitral Tribunal]

JUDGE(S): Unavailable

CASE NUMBER/DOCKET NUMBER: Unavailable

CASE NAME: Unavailable

CASE HISTORY: Unavailable

SELLER'S COUNTRY: Czech Republic [respondent]

BUYER'S COUNTRY: Germany [claimant]

GOODS INVOLVED: Cheese


Case abstract

GERMANY: Hamburg Arbitration proceeding 29 December 1998

Case law on UNCITRAL texts (CLOUT) abstract no. 293

Reproduced with permission from UNCITRAL

A German buyer, plaintiff, sued a Czech seller, defendant, for restitution of a payment made in advance for a second (out of fifteen) delivery of cheese, which had been cancelled by the seller.

The arbitral tribunal (the "tribunal") held that it had jurisdiction in the case in accordance with the arbitration clause agreed upon by the parties. In the absence of an express choice of law, the tribunal ruled that, by choosing a German place of arbitration, the parties implicitly agreed upon German law to govern the contract, and thus the CISG was applicable.

The tribunal found that the buyer was entitled to restitution of the advance payment under article 81(2) clause 1 CISG.

In view of the fact that the parties had agreed that the buyer should collect the cheese in 15 deliveries, the contract was construed to be a contract for delivery of goods by instalments under article 73 CISG.

The tribunal held that the buyer had the right to declare the contract avoided under articles 45(1)(a) and 49(1)(a) CISG. Referring to article 8 CISG, the tribunal found that an agreement on advance payment does not allow suspension of the subsequent delivery of the goods concerned on grounds such as settlement of other claims. When refusing delivery on such grounds, the seller was considered to be in fundamental breach of contract, irrespective of the existence of any other claim. Accordingly, the tribunal held that the buyer was entitled to declare the contract avoided, even without fixing an additional period of time for delivery. Although a fundamental breach of contract by one party in respect of an instalment gives the other party the right to declare the contract avoided with respect to that instalment only (article 73(1) CISG), the tribunal found that the buyer was entitled to declare the entire contract avoided, since the seller had refused to deliver further instalments (article 73(2) CISG).

The tribunal further held that the buyer's letter stating that no further business would be done with the seller had met the conditions of a declaration of avoidance under article 26 CISG.

Finally, the tribunal awarded interest from the date on which the advance payment was made according to article 84(1) CISG. The interest rate was determined under German law as applicable under the private international law provisions.

Go to Case Table of Contents


Classification of issues present

APPLICATION OF CISG: Yes [Article 1(1)(a)]

APPLICABLE CISG PROVISIONS AND ISSUES

Key CISG provisions at issue: Articles 6 ; 7(1) ; 26 ; 49(1)(a) ; 73(1) and 73(2) ; 84(1) [Also cited: Articles 4 ; 7(2) ; 8 ; 9 ; 11 ; 25 ; 30 ; 31(b) ; 47(1)(a) ; 54 ; 60 ; 61 ; 63 ; 74 ; 81(2) ; 85 ; 87 ; 88 ] [Also relevant: Articles 45 ; 72 ]

Classification of issues using UNCITRAL classification code numbers:

6B [Implied agreement to apply Convention: choice of German place of arbitration = implicit choice of German law = applicability of CISG];

7B [Materials for interpretation of Convention: international case law and scholarly studies];

26A [Notification of avoidance: effective declaration of avoidance];

49A1 [Grounds for avoidance: fundamental breach of contract];

73A ; 73B [Fundamental breach with respect to installment; Refusal of future installments];

84A [Restitution of benefits received: seller bound to refund price must pay interest]

Descriptors: Choice of law ; Internationality ; Avoidance ; Fundamental breach ; Installment contracts ; Restitution ; Interest

Go to Case Table of Contents


Editorial remarks

Go to Case Table of Contents


Citations to other abstracts, case texts and commentaries

CITATIONS TO OTHER ABSTRACTS OF DECISION

English: Unilex database <http://www.unilex.info/case.cfm?pid=1&do=case&id=394&step=Abstract>

CITATIONS TO TEXT OF DECISION

Original language (German): [1999] Neue Juristische Wochenshrift-Rechtsprechungs-Report Zivilrecht (NJW-RR) 780-782; [1999] Recht der Internationalen Wirtschaft (RIW) 394-396; Rechtsprechung Kaufmännischer Schiedsgericht, Vol. 6, E 5a no. 68; [February 2001] Internationales Handelsrecht (IHR): Zeitschrift für die wirtschaftsrechtliche Praxis 35-38; Unilex database <http://www.unilex.info/case.cfm?pid=1&do=case&id=394&step=FullText>

Translation: (English): Text presented below; see also Yearbook Commercial Arbitration (1999) 13-22

CITATIONS TO COMMENTS ON DECISION

English: Larry A. DiMatteo et al., 34 Northwestern Journal of International Law & Business (Winter 2004) 299-440 at nn.719, 813; [2005] Schlechtriem & Schwenzer ed., Commentary on UN Convention on International Sale of Goods, 2d (English) ed., Oxford University Press, Art. 8 paras. 2, 46 Art. 73 para. 23a Art. 81 para. 11 Art. 84 para. 13

Go to Case Table of Contents

Case text (English translation)

Queen Mary Case Translation Programme

Hamburg Arbitration proceeding
Award of 29 December 1998

Translation [*] by Todd Fox [**]

Translation edited by Dr Loukas Mistelis [***]

HEADNOTES [1]

1. The clause "Hamburg Friendly Arbitration" leads to the application of German procedural law and, for lack of other agreement, infers the choice of German substantive law.

2. It is sufficient under German procedural law to notify per post a foreign party not represented in Germany.

3. The arbitral tribunal also decides over the arbitration cots, including the reimbursement of out-of-court costs.

4. With the application of German substantive law the UN law on sales (CISG) applies for sales contracts between a merchant in Germany and a merchant in a foreign country, and German civil law applies to fill any gaps (for example: for the rate of interest).

5. When, under interpretation of the contract, the goods are to be delivered in individual truckloads it can be considered an installment contract.

6. The buyer can declare the installment contract avoided for the deliveries still due when the seller will only deliver for further consideration, or after prepayment makes the delivery subject to the performance of other demands.

FACTS

The [buyer] demands reimbursement of its prepayment for a non-performed delivery of 20 tons of cheese from the [seller]. This was a partial delivery out of a not fully performed contract for 300 tons of cheese. Both parties are commercial enterprises in the form of corporations. The respondent is registered in the Czech Republic as "spolecnost s rucením omezeným (spol. s. r. o.)," thus, as a Czech corporation with limited liability. On 21 January 1998 the parties agreed on delivery of 15 truckloads of cheese, 20 tons a piece, at $2,520 U.S. per ton each payable per TT [telegraphic transfer] within five days after delivery in form of collection at the plant distribution depot in the Czech Republic. G, an Austrian company acting as broker had claim to a commission. On the same day the [buyer] confirmed the purchase contract for the specified 300 tons of cheese for February at $2,520 U.S. per ton, delivery at the plant [ex warehouse], with "payment: 5 days after taking delivery." Under "special conditions" only "Hamburg Friendly Arbitration" was agreed upon. The first installment of 20 tons at $2,520 U.S. each, totaling $50,400 U.S., was, as per agreement and upon prepayment by the [buyer], loaded on to one of [buyer's] trucks on 13 February 1998. After a second prepayment of $50,400 U.S. on 16 February 1998 the second installment was not delivered. Since until the end of the February, the month for delivery in the contract, no more deliveries were made, the [buyer] demanded that the [seller] return the prepayment of $50,400 U.S. offering to cover the costs involved.

Thereafter, through intervention by G, two partial deliveries for 4 March 1998 were planned; however, the [seller] refused them.

The [buyer] initiated the arbitration proceedings of the contractually agreed upon "Hamburg Friendly Arbitration" by serving papers on the [seller]. The [buyer] demanded the return of the performed prepayment of $50,400 U.S. with interest at 9.5% from 16 February 1998. It also expressly declared the contract avoided due to non-performance and refusal to perform. The [buyer] named an arbitrator and requested the [seller] to do the same. As the [seller] delayed in naming an arbitrator, the Hamburg Chamber of Commerce named one for it upon petition by the [buyer]. The action was mostly successful.

REASONS FOR THE DECISION

I. Arbitral Tribunal

1. Arbitration Agreement

The arbitration tribunal has jurisdiction conferred upon it by the parties' written agreement to arbitrate under "Hamburg Friendly Arbitration" (see 1025 et seq., 1029, 1031(1)(2), 1040 ZPO;[2] Art. I-II UN Convention on the Recognition and Enforcement of Foreign Arbitral Awards--UN Convention--, Art. I European Convention on International Commercial Arbitration--European Convention--; see BayObLG [3] 17 September 1998 4Z Sch 1/98, RIW 1998, 965).

This arbitration clause is part of the 21 January 1998 sales contract. As is evident in the preliminary correspondence, not only the [buyer], but also the [seller] relies upon its validity.

2. Arbitration Proceedings

The arbitration proceedings of the "Hamburg Friendly Arbitrage" are governed by 20 Platzusancen [local usage] [4] for Hamburg commerce of goods (Platzusancen). According to these rules the [buyer] properly commenced the arbitration proceedings by naming an arbitrator for the dispute at issue and requesting the [seller] to also name an arbitrator ( 1044 ZPO). After the fruitless expiration of a reasonable time, the Hamburg Chamber of Commerce alternatively appointed an arbitrator on 10 July 1998 ( 20 Nr. 2 Platzusancen).

II. Applicable Procedural Law

The chosen "Hamburg Friendly Arbitration" occurs in "seat Hamburg" ( 20 Platzusancen, 1043 ZPO). Absent any other agreement German procedural law applies from this choice of seat of arbitration ( 1025(1) ZPO, Art. V(1)(d) UN Convention).

III. [Seller's] Delay

Despite the [seller's] (unexcused) delay, the arbitral tribunal must decide the dispute according to the present record ( 1048 ZPO), since the [seller] was properly put on notice of the arbitration proceedings and took no advantage of its afforded hearing (Art. V(1)(b) UN Convention, Art. IX(1)(b) European Convention).

Before the [seller's] declaration that it would neither negotiate nor comment, it was served by courier or certified mail with the arbitration commencement papers, [which included] the [buyer's] statement of claim, a deadline, a summons to an oral hearing, and an addition to the [buyer's] statement. This was the case even though it would have been enough to merely send these through the mail according to 175(1) sentence 2 ZPO, since no domestic agent had been appointed (OLG [5] Munich 30 September 1997 7 W 2520/97, RIW 1998, 969).

IV. Applicable Substantive Law

1. Choice of Law [6]

From the [Tribunal's] viewpoint the applicable substantive law is determined by German private international law (BGH [7] 24 September 1995--VII ZR 248/94, NJW 1996, 54; BB 1995, 2472).

Under German private international law the choice of arbitration venue in Hamburg not only leads to local procedural law but, absent other agreement, also to the choice of German substantive law ( 1051(1) ZPO, Art. 27 EGBGB;[8] Art. VII(1) European Convention; Arbitral Tribunal of the Hamburg Chamber of Commerce (Schiedsgericht der Handelskammer Hamburg - Arbitration Court of the Hamburg Chamber of Commerce)--SchiedsG HK-- 21 March 1996, NJW 1996, 3229, RIW 1996, 766, Cases of Commercial Arbitration (Rechtsprechung kaufmännisher Schiedsgerichte)--RKS--E 5 b Nr. 84; Palandt/Heldrich, BGB, 58th edition, Art. 27 EGBGB Rd. 6 with further references).

2. UN Sales Law

Under German as well as Czech law, UN sales law applies for sales contracts between parties in different States (United Nations Convention on Contracts for the International Sale of Goods of 11 April 1980--CISG--). Here both the prerequisites of Art. 1(1)(a) and Art. 1(1)(b) CISG are present, since the states of both parties' places of business are Contracting States (1)(a), and the rules of private international law lead to application of the law of a Contracting State (1)(b).

3. Supplementary Application of German Law

Under Art. 7(2) CISG only in so far as questions are neither settled in the CISG nor soluble according to the principles of the CISG can domestic law, as determined from the rules of private international law, be used as a supplement. Here, for purposes of supplementary application of law, the domestic law is determined to be German law.

V. [Buyer's] Principal Claim: Prepayment Reimbursement

The action for reimbursement of the performed prepayment is with merit. The [buyer] can claim repayment from the [seller] of the $50,400 U.S. for the non-performed second partial delivery under Art. 81(2) sentence 1 CISG, after it declared the (installment) contract with all outstanding partial deliveries avoided.

12. Installment Contract

The 21 January 1998 sales contract within the meaning of Art. 4 CISG in the present case is to be interpreted in accordance with Arts. 8, 9, and 11 CISG as requiring the 300 tons of cheese at $2,520 U.S. per ton in individual truckloads (15 to 20 tons) to be collected by the [buyer] in the Czech Republic. Therefore it is an installment contract within the meaning of Art. 73 CISG (see SchiedsG HK, NJW 1996, 3229, RIW 1996, 766, RKS E 5 b Nr. 84 m.w.N.; Cour d'Appel Grenoble 22 February 1995 "SARL Bri Production Bonaventure c/Sté Pan African Export," Recueil Dalloz Sirey--D.S.--1995, Informations Rapides--IR--, 100).

The [seller] was to make the goods available in the [seller's] plant distribution depot in accordance with Arts. 30 and 31(b) CISG.

This understanding comes from the context of the performance in the previous contracts as well as from the preliminary negotiations and from the performed first partial delivery on January 13, 1998 after the previous delivery date arrangement.

3. Prepayment

The rendered prepayment is, in the meaning of Art. 81(2) first sentence CISG, performance of the contract on the part of the claimant as buyer according to Art. 53 et seq. CISG. This performance was for the procurement of the [seller's] expected second partial delivery upon payment made on 16 February 1998.

Due to the actually rendered prepayment the prerequisites of Art. 81(2) CISG are already fulfilled, independent of the fact that the originally agreed upon payment conditions ("5 days after taking delivery") were changed to please the [seller] so that for the first two partial deliveries prepayment should be required.

It was repeatedly confirmed by G, and also indirectly by the [seller], that the sum paid in February was actually prepayment for the second partial delivery. Furthermore, the [seller] did not dispute this on any of the [buyer's] claims.

4. No Other Use of the Prepayment

     a) In the negotiations lead by G with the cooperation of both sides in Prague on 19 March 1998 nothing was changed concerning the purpose of the prepayment for the next partial delivery, which was still due since February.

     b) Another use of the prepayment wished by the [seller] was not agreed upon by both parties

5. Seller Has No Right to Other Set-off and to Retain the Prepayment

The [seller] may not, on the basis of legal claims under the CISG, unilaterally set-off and retain the prepayment.

The prerequisites for the [seller's] possible rights to damages (Art. 61 et seq. in conjunction with Art. 74 et seq. CISG), storage of the goods (Art. 85 in conjunction with Art. 87 CISG) or self-help sale (Art. 85 in conjunction with Art. 88 CISG) are not fulfilled.

     a) These types of seller's rights would first of all require a violation of the [buyer's] incumbent obligations as buyer to pay the sale price (Art. 54 et seq. CISG) or to take delivery (Art. 60 CISG). Such obligation violations are not evident here.

In as much as the [seller] in the preliminary correspondence asserts that the contract was not performed in its intended quantitative complete scale; this does not infer that the [buyer] did not meet its obligation to take delivery. In the extensive correspondence between the parties and G before the arbitral tribunal there is no concrete indication that the [buyer] was not prepared to take delivery of the goods placed at its disposal and -- so far not yet occurred -- prepared to pay the price in accordance with the contract. According to the [buyer's] undisputed presentation the [seller] cancelled the second partial delivery on 16 February and again on 4 March and 26 March 1998. It is shown in the correspondence that the [seller] cancelled the last two loading dates.

     b) A claim to seller's damages under Art. 61(1)(b) in conjunction with Art. 74 et seq. CISG would have furthermore first required that a reasonable additional time for the taking of delivery be set and expire or that the [buyer] give notice that it will not fulfill its obligations.

Especially concerning these prerequisites nothing is shown.

6. Contract Avoidance by the Buyer for Future Partial Deliveries

The claimant's claim as buyer under Art. 81(2) first sentence CISG for reimbursement of the prepayment first requires contract avoidance (Art. 81(1) first sentence CISG). The [buyer] effectively declared [the contract avoided] with regard to the partial delivery due and to the further due partial deliveries.

     a) The claimant's right as buyer to avoid the contract stems from Arts. 45, 47, 49 CISG, and for the installment contract from Art. 73 CISG.

aa) Avoidance of the contract by the buyer requires that the seller did not fulfill its

obligations (Art. 45(1)(a) CISG) and that such deficiency amounts to a fundamental breach (Arts. 49(1)(a), 25 CISG) or, in the case of a non-delivery, that the seller did not deliver the goods within a fixed additional period of time per Art. 47 (1) CISG or the seller declared that it would not deliver within such fixed period (Art. 49(1)(b) CISG).

Without depending on an additional fixed period of time for delivery (as here until the 4th or 26th of March 1998), the buyer can only rightly avoid the contract when the seller declares that it will not deliver at all, cannot deliver, or will only deliver for additional consideration (SchiedsG HK, NJW 1996, 3229, RIW 1996, 766, RKS E 5b Nr. 84; Huber in von Caemmerer/Schlechtriem, CISG, 2 ed. Art. 49 Rd. 6, 22).

It is an unjustified anticipatory breach when, as here, the seller, after agreeing to delivery upon prepayment, then makes its delivery dependent on the performance of other demands. Absent opposing facts, a prepayment agreement is generally -- also in international commerce (see Art. 8 CISG) -- in itself to be understood as calling for the performance in return for prepayment to be accomplished without other demands being settled beforehand (SchiedsG HK, NJW 1996, 3229, RIW 1996, 766, RKS E 5 b Nr. 84; BGH 18 May 1995 I ZR 151/93, MDR 1995, 1017 = NJW 1995, 2917).

bb) If the [seller] had insisted upon its asserted demands when it refused to make the prepayment delivery, the [buyer] would thereafter have had reason to avoid the contract in case of dispute.

cc) In the case of an installment contract, a fundamental breach of obligations concerning a partial delivery warrants avoidance of the contract for this partial delivery (Art. 73(1) CISG); an expected breach of contract for future partial deliveries allows avoidance of the contract for the future (Art. 73(2) CISG). Within the last meaning, an anticipatory breach can also pertain to all future installments and entitle the buyer to declare the contract avoided for all deliveries still due.

Such are the relations in the present dispute, since the [seller] refused not only the second partial delivery but also further deliveries under the conditions agreed upon in the installment contract. Thus, the [buyer] could declare the contract avoided for the partial delivery that was not performed upon prepayment and for all future partial deliveries under the installment contract.

     a) The [buyer] also declared its avoidance of the contract to the [seller] in accordance with Art. 26 CISG.

A fitting declaration, under Art. 11 CISG without requirements as to form, that is directed to the termination of the business relationship is sufficient for such a notice (see SchiedsG HK, NJW 1996, 3229, RIW 1996, 766, RKS E 5b Nr. 84; Leser in von Caemmerer/Schlechtriem, CISG, 2 ed. Art. 26 Rn. 8 et seq. ).

In this sense the [buyer] expressed in its fax of 26 March 1998 that it would not do any business with the [seller] in the future.

Furthermore, the [buyer] repeated the declaration of avoidance through the legal papers initiating the arbitration.

     b) Under Art. 81(2) CISG, the consequence of the buyer's (claimant's) avoidance of the contract is its claim to restitution of that which it paid. In avoiding an installment contract for the partial deliveries still due the restitution claim pertains only to that which was performed--here reimbursement of the prepayment for the unrealized second partial delivery--(see Leser in von Caemmerer/Schlechtriem, CISG, 2 ed. vor Arts. 81-84 Rd. 15).

VI. No Right to Set-Off or Right of Retention

1. As explained above in V. 4-6 a, no counterclaims of the respondent as seller--for instance, for damages--are apparent from the 21 January 1998 installment contract. Other eventual counterclaims do not entitle set-off and retention of the prepayment during the time of the delivery obligation.

2. The [seller] also has no right to set-off or retention after avoidance of the contract.

After avoidance of the contract, within the framework of reimbursement of the prepayment, a set-off or right of retention for the [seller] due to other counterclaims could be examined: for instance, counterclaims due to a possible agreement in Prague over the palette costs from earlier delivery relationships and over the payment for the delivery of labels. In this respect -- as mentioned above in IV 3 -- German law would apply to supplement the UN sales law (Art. 7(2) CISG, 387, 273 BGB).[9]

However, after avoidance of the contract and in the present arbitration proceedings the [seller] will not assert such counterclaims. As they can only be considered in case of a defense, the arbitral tribunal is not concerned with them. They can no longer be held against the present claims of the [buyer] but rather may only be pursued by the [seller] in a new arbitration proceeding. There the [seller] is at liberty to examine its pre-proceedings arguments concerning the question of the liability of the agreements made in Prague.

VII. Secondary Claim for Interest

Under Art. 84(1) CISG the seller (respondent) must pay interest on the buyer's (claimant's) prepayment reimbursement claim from the day of payment (2 February 1998).

The amount of the interest claim is attained through supplementary application of national (German) law (Art. 7(2) CISG; SchiedsG HK, NJW 1996, 3229, RIW 1996, 766, RKSE 5 p Nr. 84 m. w. N.; LG [10] Oldenburg from 9 November 1994--12 O 674/93, RIW 1996, 65).

Correspondingly, under 352 Commercial Code (HGB) [11] the [buyer] can only demand the statutory interest rate of 5% from the beginning of the interest period (16 February 1998) and, under 284, 286 BGB, can only claim the asserted overdue interest after the renewed payment request (26 March 1998).

Decision on Costs

Without agreement by the parties over the arbitration costs the arbitral tribunal must decide upon this according to 1057 ZPO, including the reimbursement of out-of-court costs (see SchiedsG HK from 21 June 1996, NJW 1997, 613, RIW 1996, 771, RKS B 5 Nr. 21 m. w. N.).

In conformity with the outcome of these proceedings the [seller] must bear the costs.


FOOTNOTES

* All translations should be verified by cross-checking against the original text. For purposes of this translation, the Claimant of Germany is referred to as [buyer]; the Respondent of Czech Republic is referred to as [seller].

** Todd Fox is an Associate of the Institute of International Commercial Law of the Pace University School of Law. He received his LL.M summa cum laude from the University of Freiburg, Germany.

*** Loukas Mistelis is Clive M Schmithoff Senior Lecturer in International Commercial Law at the School of International Arbitration and the Chair, Graduate Studies Committee, School of Law, Queen Mary, University of London.

Translator's Notes:

1. The headnotes were written by Mr. Diplom-Kaufmann Christoph Hardt, Judge for the Hamburg Tax Court (Finanzgericht).

2. Zivilprozeßordnung, the German Code of Civil Procedure.

3. Bayerisches Oberlandesgericht, the Bavarian Court of Appeal

4. Local usage - Hamburg arbitration rules.

5. Oberlandesgericht, Court of Appeal

6. Note that the Tribunal, with no apparent reason, did not apply the 1998 version of the German law. According to section 1051 the applicability of the law of the seat to the substance of the dispute is by no means automatic: Section 1051 ZPO:

"Rules applicable to substance of dispute

(1) The arbitral tribunal shall decide the dispute in accordance with such rules of law as are chosen by the parties as applicable to the substance of the dispute. Any designation of the law or legal system of a given State shall construed, unless otherwise expressed, as directly referring to the substantive law of that State and not to its conflict of laws rules.
(2) Failing any designation by the parties, the arbitral tribunal shall apply the law of the State with which the subject-matter of the proceedings is most closely connected.
[ ... ]"

Note also that the application of the law of the seat with regard to procedure is implied for proceedings held in Germany.

7. Bundesgerichtshof, the German Federal Supreme Court.

8. Einführungsgesetz zum Bürgerlichen Gesetzbuch, Introductory Act to the German Civil Code, which largely codifies German choice of law rules.

9. Bürgerliches Gesetzbuch, the German Civil Code

10. Landgericht, District Court

11. Handelsgesetzbuch, the German Commercial Code

Go to Case Table of Contents
Pace Law School Institute of International Commercial Law - Last updated August 16, 2005
Comments/Contributions
Go to Database Directory || Go to CISG Table of Contents || Go to Case Search Form || Go to Bibliography