Reproduced with permission of the author
Practical Considerations in International
Infrastructure Investment and Finance
Frederick R. Fucci
Thelen Reid & Priest LLP
American Bar Association
Section of International Law
Spring Meeting (April 2006)
"... Just as the Company cannot not argue that it should not be required to bear any increase in the price ... it would be totally excessive if it is admitted that such increases are to be considered a normal business risk; on the contrary, it is necessary to find a solution that puts an end to temporary difficulties, taking into account both the general interest ... and the special conditions that do not allow the contract to operate normally ...; to this end it is necessary to decide, on the one hand, that the Company is required to provide the concession service and, on the other hand, that during this period it must bear only that part of the adverse consequences that a reasonable interpretation of the contract allows ..."[6]
| (a) | Delay in delivery or non-delivery in whole or in part by a seller . . . is not a breach of his duty under a contract for sale if performance as agreed has been made impracticable by the occurrence of a contingency the non-occurrence of which was a basic assumption on which the contract was made or by compliance in good faith with any applicable foreign or domestic governmental regulation or order whether or not it later proves to be invalid. |
In situations in which neither sense nor justice is served by either answer when the issue is posed in flat terms of 'excuse' or 'no excuse', adjustment under the various provisions of this Article is necessary, especially the sections on good faith, on insecurity and assurance and on the reading of all provisions in the light of their purposes, and the general policy of this Act to use equitable principles in furtherance of commercial standards and good faith.
There is hardship where the occurrence of events fundamentally alters the equilibrium of the contract either because the cost of a party's performance has increased or because the value of the performance a party receives has diminished, and
| (a) | the events occur or become known to the disadvantaged party after the conclusion of the contract; |
| (b) | the events could not reasonably have been taken into account by the disadvantaged party at the time of the conclusion of the contract; |
| (c) | the events are beyond the control of the disadvantaged party; and |
| (d) | the risk of events was not assumed by the disadvantaged party.[23] |
II. QUESTIONS FOR INVESTORS AND LENDERS
The principle of rebus sic stantibus is universally considered as being of strict and narrow interpretation, as a dangerous exception to the principle of sanctity of contracts. Whatever opinion or interpretation lawyers of different countries may have about the 'concept' of changed circumstances as an excuse for non-performance, they will doubtless agree on the necessity to limit the application of the so-called 'doctrine rebus sic stantibus' (sometimes referred to as 'frustration', 'force majeure', imprévision', and the like) to cases where compelling reasons [emphasis in original] justify it, having regard not only to the fundamental character of the changes, but also to the particular type of contract involved, to the requirements of fairness and equity and to all circumstances of the case.
It should be obvious that none of the requirements which might justify the application of the 'doctrine' are fulfilled in this case. As a general rule, one should be particularly reluctant to accept it when there is no gap or lacuna in the contract and when the intent of the parties has been clearly expressed, as in the Bank Guarantee. Caution is especially called for, moreover, in international transactions where it is generally much less likely that the parties have been unaware of the risk of a remote contingency or unable to formulate it precisely.
The Tribunal is convinced that the Argentine crisis was severe, but did not result in total economic and social collapse. When the Argentine crisis is compared to other contemporary crises affecting countries in different regions of the world it may be noted that such other crises have not led to the derogation of international contractual or treaty obligations. Renegotiation, adaptation and postponement have occurred, but the essence of the international obligations has been kept intact.[65]
"If the thesis of Air France were to be accepted, it would become much too easy for companies submitted to the supervision (tutelle) of the State to exonerate themselves from their obligations ... In fact, in relation to third parties, such a company and the State form one and the same legal entity; the intervention of the public authority, which is organically linked to the normal functioning of the company, does not constitute an outside event which can be invoked against third persons and contracting parties."
Even in the absence of a provision by the parties, their intent must reasonably be interpreted as rejecting the external nature of acts of those state organs which play an institutional role in the functioning of the state legal entity. Thus, when a state entity is subject to the supervision of a ministry, the intervention of the latter may be assimilated to an element of its own decision process, even if it is presented as being external. It is not a question of denying the distinction between the personality of the state and that of its agency, but simply to consider that one who contracts with a supervised entity is normally not ready to admit that the supervisory authority may discharge it of its obligations.[72]
State-controlled enterprises, with legal personality, ability to trade and to enter into contracts of private law, though wholly subject to the control of the state, are a well-known feature of the modern commercial scene. The distinction between them, and their governing state, may appear artificial, but it is an accepted distinction in the law of England and other states.
[E]ach contracting party who is temporarily prevented from performing its contractual obligations has the general duty of good faith to make efforts to that end.
The Government has the duty to redress this abnormal situation, first, by putting an end to what by definition should be a temporary situation, a step that might be adequately taken in the context of the continuing negotiations between the parties, and next by paying compensation for the damage caused.[92]