Article 71

(1) A party may suspend the performance of his obligations if, after the conclusion of the contract, it becomes apparent that the other party will not perform a substantial part of his obligations as a result of:

(a) a serious deficiency in his ability to perform or in his creditworthiness; or

(b) his conduct in preparing to perform or in performing the contract.

(2) If the seller has already dispatched the goods before the grounds described in the preceding paragraph become evident, he may prevent the handing over of the goods to the buyer even though the buyer holds a document which entitles him to obtain them. The present paragraph relates only to the rights in the goods as between the buyer and the seller.

(3) A party suspending performance, whether before or after dispatch of the goods, must immediately give notice of the suspension to the other party and must continue with performance if the other party provides adequate assurance of his performance.

Legislative history || Case law || Scholarly writings || Links to related articles || Words and phrases || CISG (full-text)


Guide to this article


Legislative history


Case law


Scholarly writings on this article

The cisgw3 bibliography contains over 8,000 citations. It is therefore likely that, in addition to case law, you will find scholarly literature - often a wealth of such literature - on virtually every aspect of the CISG you research.


Links to related articles


Words and phrases encountered in Article 71


Pace Law School Institute of International Commercial Law - Last updated January 15, 2014
Comments/Contributions
Go to Database Directory || Go to Table of Contents to Annotated Text of CISG